Work Progress: 2011-03-31 [DAY 172] Site Office & Show Units (Kongsi) II.


31-03-2011 [DAY 172] Surrounding works at site office & show units. Advertisements

Posted in Work Progress | Tagged , , , , , , , , , | Leave a comment

Work Progress: 2011-03-26 [DAY 167] Drainage II. (UPDATED!)


26-03-2011 [DAY 167] UPDATED! The first 100m of drainage laid in place.

Posted in Work Progress | Tagged , , , , , , | 5 Comments

Work Progress: 2011-03-01 [DAY 142] Site Office & Showhouse.


01-03-2011 [DAY 142] Site office & Show Units.

Posted in Work Progress | Tagged , , , , , , , , , | Leave a comment

Work Progress: 2011-01-31 [DAY 113] Kongsi, Piling, Road.


31-01-2011 [DAY 113] Continuous work on Kongsi and road. Also beginning of next step…piling.

Posted in Work Progress | Tagged , , , , , , | Leave a comment

Work Progress: 2011-01-08 [Day 090] Roads, Drains & Hoarding.


08-01-2011 [DAY 090] You may not see much happenning in this progress report but this is essentially the first important step towards the rest of the project. There’ll be more updates to come. See what we’ve done so far inside.

Posted in Work Progress | Tagged , , , , , , | Leave a comment