Work Progress 2017-04-17 Shops

This gallery contains 3 photos.


Advertisements

Gallery | Leave a comment

Work Progress 2017-01-15

This gallery contains 9 photos.


Gallery | Leave a comment

Work Progress 2016-10-06


Block 1 – Continue install ceiling at sample unit

img-20161006-wa0011

2016 10 05

Block 1 – Water tank installed

20161005_153236

Block 1 – After concrete then prepare to install HR drain

Block 1 – Continue to install ceiling at sample unit

2016 10 04

Block 1 – Front drain excavate and concrete

Block 1 – Left side ceiling done and installing for back ceiling at sample unit

2016 09 30

Block 1 – Ground floor sample unit ceiling installation on left side

img-20160930-wa0000

Welding hollow for water tank

img-20160930-wa0001

Cement deliver to site

img-20160930-wa0015

2016 09 29

Block 1 – Ceiling at ground floor

Welder welding for water tank support

Block 1 – Middle drain

img-20160929-wa0047

Drain cover concreting

img-20160929-wa0048

2016 09 28

Block 1 – Laying bricks at middle drain

Block 1 – Install ceiling at ground floor show unit

20160928_154300

Block 1 – Installing wall board at 3rd floor

 

2016 09 27

BLock 1 – Loading floor board for 1st and 2nd floor at 7th unit

20160927_16535420160927_165412

Sand deliver to site

img-20160927-wa0012

2016 09 26

Block 1 – Painting hollow section

20160926_134939

Block 1 – Installing floor board at 6th unit ground floor

20160926_135101

Block 1 – Bricks laying for rear and middle drain

UoB banker come to site for inspection

20160926_16054920160926_16075520160926_16090720160926_16115820160926_161623

2016 09 22

Block 1 – Rear and middle drain in progress

Removing drain cover which formed20160922_160111

Welder welding at Block 1

Block 1 – Installing floor board at 6th unit 1st floor

20160922_16085020160922_163050

Block 1 – Painter skim and painting at ground floor

20160922_161451

2016 09 21

Gen-set repaired by repair man

img-20160921-wa0025

BRC deliver to site

img-20160921-wa0042

2016 09 20

Block 1 – Installing floor board at 6th unit 2nd floor

20160920_161655

Block 1 – Concreting middle drain

Welding angles

Block 1 – Continue rear drain

2016 09 19

Painter skimming 1st floor external wall

20160919_095648

Bricks deliver to site

20160919_121424

Aggregate deliver to site

img-20160919-wa0003

Block 1 – Bricks laying at rear drain

img-20160919-wa0009

2016 09 15

Drain cover in progress

20160915_091726

Earthwork

20160915_093714

Painter continue skim external wall

20160915_094932

Posted in Uncategorized | Leave a comment

Work Progress


2016 08 26

Block 1 – New welding machine bought to site. Continue welding on 1st floor, 3rd unit.

Block 1 – 1st floor Floor board installing.

Block 11- Middle drain

Continue another batch of drain cover

20160826_14592520160826_155256

Electrician installing wire and points at sample unit.

2016 08 29

Block 1 – Welding on 2nd floor, 3rd unit.

Block 1 – Floor installing at ground floor, 4th unit.

20160829_093436

Preparation for another batch drain cover.

Block 11 – Excavating & concreting middle and right side drain.

Installing naco at sample unit

20160829_113218

2016 08 30

Block 1 – Electrician installing power outlets and switches at sample unit

20160830_09560820160830_095631

Sand delivered to site

20160830_095027

2016 09 01

Block 1 – Finish up naco installation.

20160901_091711

Prepare for another batch of drain cover

20160901_092336

Block 11 – Prepare to install HR drain.

20160901_092521

Block 1 – Continue installing hollow at 3rd unit 2nd floor.

20160901_09501820160901_095035

2016 09 02

Repaired welding machine bought to site.

20160902_143934

Block 11 – Working on right side drain

20160902_161756

Block 3 – Plastering middle drain

20160902_162359

2016 09 05

Block 3 – Covering drain cover at middle drain

20160905_093836

Remove completed drain cover and continue concrete for next batch drain cover

Block 11 – continue finish middle drain

20160905_09435920160905_094552

Block 1 – Excavating rear side drain

Block 1 – installing floor board at 5th unit ground floor

20160905_10525520160905_171431

Cement board deliver to site

Electrician do wiring at ground floor sample unit

Excavator tracks pad / tracks chain off track.

20160905_140937

Welder welding roof trusses

20160905_171533

2016 09 06

Cement Board deliver to site

Block 3 – Completing drain

Block 1 – Continue finish 5th unit ground floor floor board

20160906_11310520160906_163220

Block 1 – Welder welding roof truss

Continue excavating Block 1 rear drain

Drain cover in process

20160906_113822

Plastering before drain cover

20160906_140553

2016 09 07

Lorry deliver BRC to site

IMG-20160907-WA0004.jpg

2016 09 08

Block 1 – Welder welding and carry roof truss to the top.

Block 1 – Floor board installing at 5th unit 2nd floor

20160908_09122320160908_154731

Removing completed drain cover and continue another pour.

Block 1 – Concreting rear drain

HR drain deliver to site

20160908_16430620160908_171236

Cement deliver to site

2016 09 09

Block 1 – Excavating middle drain

img-20160909-wa0009

2016 09 13

Block 1 – Installing HR drain

img-20160913-wa0004

2016 09 14

Block 1 – Painter skimming external wall.

Block 1 – Installing floor board at 5th unit 1st floor

Block 1 – Welding and installing roof truss

Drain cover

Block 1 – Bricks laying for rear drain

20160914_094329

Block 1 – Loading floor board to 1st and 2nd floor

20160914_134409

 

Posted in Uncategorized | Leave a comment

2016 08 25


Block 1 – Electrician fixing 1st floor wire.

Block 1 – 2nd floor Floor board installed

20160825_124539

Block 11 – Drain continue bricks laying

Architect come to site

20160825_162948

Posted in Uncategorized | Leave a comment