Work Progress 2016-10-06


Block 1 – Continue install ceiling at sample unit 2016 10 05 Block 1 – Water tank installed Block 1 – After concrete then prepare to install HR drain Block 1 – Continue to install ceiling at sample unit 2016 … Continue reading

Posted in Uncategorized | Leave a comment

Work Progress


2016 08 26 Block 1 – New welding machine bought to site. Continue welding on 1st floor, 3rd unit. Block 1 – 1st floor Floor board installing. Block 11- Middle drain Continue another batch of drain cover Electrician installing wire … Continue reading

Posted in Uncategorized | Leave a comment

2016 08 25


Block 1 – Electrician fixing 1st floor wire. Block 1 – 2nd floor Floor board installed Block 11 – Drain continue bricks laying Architect come to site

Posted in Uncategorized | Leave a comment

Work Progress


2016 08 24 Drain cover done and cover to Block 3 drain Block 11 – HR Drain installed and bricks work laying Welder Welding machine spoil Block 1 – Continue install floor board at 3rd unit 2016 08 23 Welding … Continue reading

Posted in Uncategorized | Leave a comment

Work Progress


2016 08 11 Block 1 – Welding and installing floor board at 3rd unit Cement delivered to site Block 3 – Bricks installing on the left side drain and start level and install HR drain for the right side drain … Continue reading

Posted in Uncategorized | Leave a comment