Work Progress


2016 10 06

Block 1 – Continue install ceiling at sample unit

img-20161006-wa0011

2016 10 05

Block 1 – Water tank installed

20161005_153236

Block 1 – After concrete then prepare to install HR drain

Block 1 – Continue to install ceiling at sample unit

2016 10 04

Block 1 – Front drain excavate and concrete

Block 1 – Left side ceiling done and installing for back ceiling at sample unit

2016 09 30

Block 1 – Ground floor sample unit ceiling installation on left side

img-20160930-wa0000

Welding hollow for water tank

img-20160930-wa0001

Cement deliver to site

img-20160930-wa0015

2016 09 29

Block 1 – Ceiling at ground floor

Welder welding for water tank support

Block 1 – Middle drain

img-20160929-wa0047

Drain cover concreting

img-20160929-wa0048

2016 09 28

Block 1 – Laying bricks at middle drain

Block 1 – Install ceiling at ground floor show unit

20160928_154300

Block 1 – Installing wall board at 3rd floor

 

2016 09 27

BLock 1 – Loading floor board for 1st and 2nd floor at 7th unit

20160927_16535420160927_165412

Sand deliver to site

img-20160927-wa0012

2016 09 26

Block 1 – Painting hollow section

20160926_134939

Block 1 – Installing floor board at 6th unit ground floor

20160926_135101

Block 1 – Bricks laying for rear and middle drain

UoB banker come to site for inspection

20160926_16054920160926_16075520160926_16090720160926_16115820160926_161623

2016 09 22

Block 1 – Rear and middle drain in progress

Removing drain cover which formed20160922_160111

Welder welding at Block 1

Block 1 – Installing floor board at 6th unit 1st floor

20160922_16085020160922_163050

Block 1 – Painter skim and painting at ground floor

20160922_161451

2016 09 21

Gen-set repaired by repair man

img-20160921-wa0025

BRC deliver to site

img-20160921-wa0042

2016 09 20

Block 1 – Installing floor board at 6th unit 2nd floor

20160920_161655

Block 1 – Concreting middle drain

Welding angles

Block 1 – Continue rear drain

2016 09 19

Painter skimming 1st floor external wall

20160919_095648

Bricks deliver to site

20160919_121424

Aggregate deliver to site

img-20160919-wa0003

Block 1 – Bricks laying at rear drain

img-20160919-wa0009

2016 09 15

Drain cover in progress

20160915_091726

Earthwork

20160915_093714

Painter continue skim external wall

20160915_094932

This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s