2016 08 26

Block 1 – New welding machine bought to site. Continue welding on 1st floor, 3rd unit.

Block 1 – 1st floor Floor board installing.

Block 11- Middle drain

Continue another batch of drain cover

20160826_14592520160826_155256

Electrician installing wire and points at sample unit.

2016 08 29

Block 1 – Welding on 2nd floor, 3rd unit.

Block 1 – Floor installing at ground floor, 4th unit.

20160829_093436

Preparation for another batch drain cover.

Block 11 – Excavating & concreting middle and right side drain.

Installing naco at sample unit

20160829_113218

2016 08 30

Block 1 – Electrician installing power outlets and switches at sample unit

20160830_09560820160830_095631

Sand delivered to site

20160830_095027

2016 09 01

Block 1 – Finish up naco installation.

20160901_091711

Prepare for another batch of drain cover

20160901_092336

Block 11 – Prepare to install HR drain.

20160901_092521

Block 1 – Continue installing hollow at 3rd unit 2nd floor.

20160901_09501820160901_095035

2016 09 02

Repaired welding machine bought to site.

20160902_143934

Block 11 – Working on right side drain

20160902_161756

Block 3 – Plastering middle drain

20160902_162359

2016 09 05

Block 3 – Covering drain cover at middle drain

20160905_093836

Remove completed drain cover and continue concrete for next batch drain cover

Block 11 – continue finish middle drain

20160905_09435920160905_094552

Block 1 – Excavating rear side drain

Block 1 – installing floor board at 5th unit ground floor

20160905_10525520160905_171431

Cement board deliver to site

Electrician do wiring at ground floor sample unit

Excavator tracks pad / tracks chain off track.

20160905_140937

Welder welding roof trusses

20160905_171533

2016 09 06

Cement Board deliver to site

Block 3 – Completing drain

Block 1 – Continue finish 5th unit ground floor floor board

20160906_11310520160906_163220

Block 1 – Welder welding roof truss

Continue excavating Block 1 rear drain

Drain cover in process

20160906_113822

Plastering before drain cover

20160906_140553

2016 09 07

Lorry deliver BRC to site

IMG-20160907-WA0004.jpg

2016 09 08

Block 1 – Welder welding and carry roof truss to the top.

Block 1 – Floor board installing at 5th unit 2nd floor

20160908_09122320160908_154731

Removing completed drain cover and continue another pour.

Block 1 – Concreting rear drain

HR drain deliver to site

20160908_16430620160908_171236

Cement deliver to site

2016 09 09

Block 1 – Excavating middle drain

img-20160909-wa0009

2016 09 13

Block 1 – Installing HR drain

img-20160913-wa0004

2016 09 14

Block 1 – Painter skimming external wall.

Block 1 – Installing floor board at 5th unit 1st floor

Block 1 – Welding and installing roof truss

Drain cover

Block 1 – Bricks laying for rear drain

20160914_094329

Block 1 – Loading floor board to 1st and 2nd floor

20160914_134409

 

This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s