Work Progress


2016 08 11

Block 1 – Welding and installing floor board at 3rd unit

Cement delivered to site

20160811_131204

Block 3 – Bricks installing on the left side drain and start level and install HR drain for the right side drain

2016 08 10

Block 1 – Loading floor board to 2nd floor

Concrete Mixer spoiled, sending to repair

20160810_11375320160810_113915

Block 1 – Aluminum window installed at sample unit

Sand and stone delivered to site

Block 1 – Welding on 2nd floor

20160810_134607

Block 3 – Leveling and install HR Drain.

2016 08 09

Installing door frame at sample unit

20160809_115234

Welding hollow for floor board

20160809_135222

Block 1 – Floor board installed at 1st floor, 2nd unit

20160809_171748

2016 08 08

Block 1 – Installing 1st floor floor board

Concrete Block 3 drain

2016 08 05

Block 1 – installing 2nd unit floor board

20160805_09284220160805_163321

Excavating & concrete drain at block 3

Excavating middle drain

Plaster for drain Sump

20160805_134300

2016 08 04

Block 1 – Continue work on floor board

20160804_091112

Block 3 – Plastering U drain and bricks laying for drain sump

2016 08 03

Block 1 – Installing floor board

Block 3 – Concreting drain

2016 08 02

Wall board installed at 1st floor sample unit

Installing Floor board at Block 1

2016 08 01

Block 3 – U Drain installed

20160801_161758img-20160801-wa0002img-20160801-wa0003

2016 07 29

Aluminum window frame installed at sample unit

Welding at 1st floor sample unit

2016 07 28

Block 3 – Excavation for drain and concreting base

Partition at second floor sample unit

20160728_11503120160728_115045

2016 07 27

Rockwool installed before wall board.

Pipe installed by electrician for wiring

img-20160727-wa0018

Cement board delivered to site

20160727_15241120160727_152834

2016 07 26

Block 3 – Right Drain

20160726_134448

U Drain for Block 3 drain

20160726_160233

Bricks delivered to site

Water pipe installed

Sand delivered to site

img-20160726-wa0022

2016 07 25 – Block 3 Drain

Brick Work start after Concrete and HR Drain lay.

Cement arrived

img-20160725-wa0001

Water pipe install at 3rd floor of sample unit

20160725_160213

3rd floor partition done, then continue on 2nd floor

2016 07 22

Block 3 – Bricks laying

img-20160722-wa0005

Formwork continue

img-20160722-wa0008

Fixing wall board after weld.

img-20160722-wa0014

2016 07 21 – 3rd Floor Partition

Welding Hollow for Partition

20160721_15353520160721_153525

Block 3 – HR Drain installed for middle drain

20160721_10522020160721_105155

Formwork for concrete

20160721_155529

2016 07 20 – Partition in Sample Unit

Welding Hollow for Partition

20160720_12332420160720_12333820160720_134143

Block 3 – Concrete for middle drain

20160720_125112

This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s