Work Progress

Week 30 – Drainage installation


Roof Completed


Formwork for lean concrete


Week 29 – Roof arrived

Sanitary piping installation

Concrete for drain

Week 28 – Sanitary & water piping


Week 27 – Aluminum door and window installation


Week 26 – Roof truss installation


Week 21 – Wall painted


Week 20 – Door Frame arrived

Week 18 – Block Pegging

Angle bar installation