Monthly Archives: July 2016

Work Progress


Week 30 – Drainage installation Roof Completed Formwork for lean concrete   Week 29 – Roof arrived Sanitary piping installation Concrete for drain Week 28 – Sanitary & water piping   Week 27 – Aluminum door and window installation   … Continue reading

Posted in Uncategorized | 1 Comment