Monthly Archives: March 2011

Work Progress: 2011-03-26 [DAY 167] Drainage II. (UPDATED!)


26-03-2011 [DAY 167] UPDATED! The first 100m of drainage laid in place. Advertisements

Posted in Work Progress | Tagged , , , , , , | 5 Comments

Work Progress: 2011-03-24 [DAY 165] Drainage.


24-03-2011 [DAY 165] Works on drainage started today as what you can see in the photos. Of course we’ll start with the shops first.

Posted in Work Progress | Tagged , , , , , | Leave a comment

Work Progress: 2011-03-15 [DAY 156] Site Office & Showhouse II.


15-03-2011 [DAY 156] Many of you actually came by to see the progress of work and we appreciate your support. Well you didn’t go back disappointed from what you’ve seen…

Posted in Work Progress | Tagged , , , , , , , | Leave a comment

Work Progress: 2011-03-03 [DAY 144] Site Office & Showhouse.


03-03-2011 [DAY 144] Site office will be ready and operational by next week.

Posted in Work Progress | Tagged , , , , , , , | 1 Comment

Work Progress: 2011-03-01 [DAY 142] Site Office & Showhouse.


01-03-2011 [DAY 142] Site office & Show Units.

Posted in Work Progress | Tagged , , , , , , , , , | Leave a comment